RT I590: I390 TO HIGHLAND AVE & I390 AT I590 INTERCHANGE MBC
Project ID No. 459019 , Contract Number D262910
Description
This project involves resurfacing the pavement on I-590 from I-390 to Highland Avenue and I-390 at I-590 Interchange in the Town of Brighton and the City of Rochester, Monroe County. This project will improve the driving surface for the traveling public and extend the service life of the pavement.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 08/20/2015
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 09/17/2015 | 11/30/2016 | 12/28/2016 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $9,920,001 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the GENESEE VALLEY region and includes the following:
Counties
MONROE
Towns
BRIGHTON
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
25th Congressional District (Joseph Morelle)
State Senatorial District(s)
56th Senatorial District (Jeremy Cooney)
State Assembly District(s)
136th Assembly District (Sarah Clark)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
1530 Jefferson Road
Rochester, NY 14623
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov