Project Details

I-390 AT RT 383 (SCOTTSVILLE RD) INTERCHANGE SAFETY ENHANCEMENTS

Project ID No. 439096 , Contract Number D264936

Description

This project proposes to provide safety enhancements at the I-390 ramps and Route 383 intersections. Proposed improvements consist of ramp realignments, widening for additional lanes and traffic signal improvements. Town of Chili, Monroe County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 03/09/2023

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
04/21/2023 12/31/2024 10/16/2024 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,553,693 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the GENESEE VALLEY region and includes the following:

Counties
MONROE

Towns
CHILI

04 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
25th Congressional District (Joseph Morelle)

State Senatorial District(s)
54th Senatorial District (Pamela Helming)

State Assembly District(s)
138th Assembly District (Harry B. Bronson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Mare Millow
1530 Jefferson Road
Rochester, NY 14623
Phone: 585-272-4818
Email: mare.millow@dot.ny.gov
Provide feedback on this project