INTERSTATE MOWING AND ROADSIDE CLEANUP PROJECT
Project ID No. 3M1000 , Contract Number D265013
Description
Several times during the warmer weather months, this project will clean shoulders and roadsides and mow grassy areas along the interstate highways in and around the City of Syracuse. The work areas include: I-81 between the north and south I-481 interchanges; portions of I-481 and NY 481 in and near the I-81 and I-690 intrchanges; and I-690 from Exit 5 (State Fair Boulevard) to Exit 17 (Bridge Street). This project covers litter/debris cleanup, sweeping and mowing operations in these areas for 2023 and 2024.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 04/06/2023
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 06/02/2023 | 07/01/2025 | 06/09/2025 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $1,731,124 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: No
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CENTRAL NEW YORK region and includes the following:
Counties
ONONDAGA
Cities
SYRACUSE
Towns
CICERO
CLAY
DE WITT
GEDDES
ONONDAGA
SALINA
Villages
NORTH SYRACUSE
EAST SYRACUSE
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
22th Congressional District (John Mannion)
State Senatorial District(s)
48th Senatorial District (Rachel May)
50th Senatorial District (Christopher J. Ryan)
State Assembly District(s)
127th Assembly District (Al Stirpe)
128th Assembly District (Pamela J. Hunter)
129th Assembly District (William B. Magnarelli)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov