Project Details

VPP/MILL, RT 481, SENECA ST TO CR 57 N OF FULTON, OSWEGO COUNTY

Project ID No. 360465

Description

This project will remove and replace the top 2.25 inches of asphalt on Route 481 from Seneca Street in the City of Fulton north to County Route 57, a distance of nearly 4 miles in the City of Fulton and Town of Volney, Oswego County.  Route 481 at Route 3 and Route 481 at County Route 57 south of Fulton will be addressed as well.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 03/11/2026

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
05/01/2026 N/A N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$2,207,688 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CENTRAL NEW YORK region and includes the following:

Counties
OSWEGO

Cities
FULTON

Towns
VOLNEY

03 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
24th Congressional District (Claudia Tenney)

State Senatorial District(s)
50th Senatorial District (Christopher J. Ryan)

State Assembly District(s)
120th Assembly District (William A. Barclay)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

TeNesha Murphy - Region 3 Public Information Officer
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov
Provide feedback on this project