STATE FAIRGROUNDS ACCESS IMPROVEMENT PROJECT PHASE 1
Project ID No. 350651 , Contract Number D263545
Description
This two-phase project will improve access between Interstate 690 and the New York State Fair's upper (orange) parking lot, to greatly reduce or eliminate traffic backups on the highway on high attendance days and to generally improve mobility in the area. The proposed elements of Phase 1 work include paving and striping the upper lot, including handicapped accessible spaces; construction of internal access and circulation roads; new lighting and drainage systems and a new on-ramp from the upper lot to westbound I-690. This work is scheduled to take place in the period between the end of the 2017 NYS Fair and the beginning of the 2018 Fair, with a break over the winter.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 09/07/2017
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 10/04/2017 | 08/15/2018 | 10/31/2018 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $27,238,115 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: No
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CENTRAL NEW YORK region and includes the following:
Counties
ONONDAGA
Towns
GEDDES
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
22th Congressional District (John Mannion)
State Senatorial District(s)
50th Senatorial District (Christopher J. Ryan)
State Assembly District(s)
129th Assembly District (William B. Magnarelli)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351