MBC - 81I, CORTLAND COUNTY LINE TO N OF RT 20, ONONDAGA CO
Project ID No. 350175 , Contract Number D263639
Description
This milling and resurfacing project will restore a smooth riding surface to the 8.9 mile portion of I-81 from the Cortland County line to the Route 11 onramp to I-81 north of Route 20. The raised joints will be ground down and reconstructed prior to the placement of an asphalt overlay. Traffic will be maintained on-site using daily lane closures. This work will take place in the towns of Tully and LaFayette, in Onondaga County.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 01/11/2018
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 02/05/2018 | 11/30/2018 | 11/26/2018 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $8,224,111 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CENTRAL NEW YORK region and includes the following:
Counties
CORTLAND
ONONDAGA
Towns
LAFAYETTE
PREBLE
TULLY
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
22th Congressional District (John Mannion)
State Senatorial District(s)
48th Senatorial District (Rachel May)
State Assembly District(s)
126th Assembly District (John Lemondes)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov