This project will replace deficient, damaged, non-reflective, missing or worn roadside delineators and small ground mounted warning, guide and regulatory signs along Interstate 81 between the southern interchange with I-481 and 0.5 miles south of the Cortland County line, a distance of 17 miles, in Onondaga and Cortland Counties.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 03/09/2017
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 03/30/2017 | 12/15/2017 | 12/28/2017 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $1,313,199 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CENTRAL NEW YORK region and includes the following:
Counties
CORTLAND
ONONDAGA
Cities
SYRACUSE
Towns
LAFAYETTE
ONONDAGA
PREBLE
TULLY
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
22th Congressional District (John Mannion)
State Senatorial District(s)
48th Senatorial District (Rachel May)
52th Senatorial District (Lea Webb)
State Assembly District(s)
126th Assembly District (John Lemondes)
128th Assembly District (Pamela J. Hunter)
129th Assembly District (William B. Magnarelli)
131th Assembly District (Jeff Gallahan)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov