Description
This safety project will reconstruct the intersection of NY 481 and Oswego County Route 45 in the towns of Scriba and Volney, Oswego County. The existing layout allows traffic on CR 45 to cross one direction of 481, then wait in the median prior to crossing the other direction of 481. The new intersection, called a "Restricted Crossing U-Turn" (RCUT), forces cross traffic to merge onto NY 481, make a U-turn through the median approximately 800 feet from CR 45, then come back towards CR 45. It reduces the number of intersection conflict points.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 12/14/2017
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 01/23/2018 | 11/30/2018 | 11/29/2018 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $1,898,545 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CENTRAL NEW YORK region and includes the following:
Counties
OSWEGO
Towns
SCRIBA
VOLNEY
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
24th Congressional District (Claudia Tenney)
State Senatorial District(s)
50th Senatorial District (Christopher J. Ryan)
State Assembly District(s)
120th Assembly District (William A. Barclay)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov