RT 635 (THOMPSON RD) AT EB SERVICE RD TO I-690
Project ID No. 310422 , Contract Number D263721
Description
This project will re-align the ramp from southbound Thompson Road to the eastbound I-690 service road to reduce the number of rear-end and right angle crashes which occur at the intersection of the ramp and the service road. These accidents occur due to the skew angle of this intersection, the anticipation of the vehicle movement with the vehicles waiting in front of them, and the speed of vehicles exiting I-690 to the eastbound service road. By realigning the lower section of the Thompson Road ramp to lessen the skew, the drivers will be able to look at vehicles coming along the service road as well as looking at the vehicles also stopped in front of them at the intersection.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 06/07/2018
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 07/10/2018 | 10/31/2018 | 10/05/2018 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $298,269 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: No
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CENTRAL NEW YORK region and includes the following:
Counties
ONONDAGA
Cities
SYRACUSE
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
22th Congressional District (John Mannion)
State Senatorial District(s)
48th Senatorial District (Rachel May)
State Assembly District(s)
129th Assembly District (William B. Magnarelli)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov