Project Details

RT. 104, RT 104A TO OSWEGO CITY LINE, OSWEGO CO

Project ID No. 304552 , Contract Number D263123

Description

This 3.7 mile project along Route 104, from the intersection of Route 104A to the City of Oswego west city line, will include a two course asphalt resurfacing; provide 11' wide travel lanes and 8' wide shoulders; improve sight lines at the County Route 20 and 89 intersections; improve the entrance to SUNY Oswego and the Fifth Avenue intersection; install new curbing, drainage systems, and a sidewalk along the north side of Route 104 between Sweet Road and the west city line. Traffic will be maintained on-site during the phased construction process.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 04/14/2016

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
05/19/2016 11/30/2017 06/29/2018 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$14,088,750 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CENTRAL NEW YORK region and includes the following:

Counties
OSWEGO

Cities
OSWEGO

Towns
OSWEGO

03 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
24th Congressional District (Claudia Tenney)

State Senatorial District(s)
50th Senatorial District (Christopher J. Ryan)

State Assembly District(s)
120th Assembly District (William A. Barclay)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

TeNesha Murphy - Region 3 Public Information Officer
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov
Provide feedback on this project