Project Details

PIL 2015-2018 Rt 481 NB Off Ramp at Circle Drive(Rt 931H) Safety Improvements and Rt 481 Barrier Safety Improvements, Town of Cicero and Village of North Syracuse, Onondaga County

Project ID No. 304369 , Contract Number D265304

Description

This project will add median barriers to the Route 481 Northbound (Exit 10) off-ramp. The improvements will address long queues, as well as rear end and side-swipe crashes on the exit ramp.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 09/12/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
10/09/2024 11/15/2025 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$2,975,334 $93,731 $3,069,065 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CENTRAL NEW YORK region and includes the following:

Counties
ONONDAGA

Towns
CICERO

Villages
NORTH SYRACUSE

03 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
22th Congressional District (John Mannion)

State Senatorial District(s)
50th Senatorial District (Christopher J. Ryan)

State Assembly District(s)
127th Assembly District (Al Stirpe)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

TeNesha Murphy - Region 3 Public Information Officer
333 E. Washington Street
Syracuse, NY 13202
Phone: 315-428-4351
Email: tenesha.murphy@dot.ny.gov
Provide feedback on this project