Project Details

EMPIRE STATE TRAIL: DYKE ROAD TO ACME RD, HERK. CO

Project ID No. 2EST01 , Contract Number D263874

Description

This project establishes a 7.8 mile on-road segment of the Empire State Trail through the Village of Frankfort and the Towns of Frankfort and Schuyler in Herkimer County. At its western project limit, the Empire State Trail connects to an off-road segment of the trail at the bridge carrying Dyke Rd (County Route 37) over the New York State Thruway in the Town of Schuyler. From this point, the Trail proceeds south along Dyke Road and Dyke Road Spur to Southside Road in the Town of Frankfort. It continues through the Town and Village of Frankfort along Southside Road, West Main Street, East Main Street, and Acme Rd to the eastern project limit at the interchange with New York State Route 5S. Here, the on-road segment of the Empire State Trail connects with an off-road segment from the east. The four lane section of Acme Road will be restriped as a three lane section with shoulders to accommodate pedestrians and bicyclists. Pavementrepairswill be made along the route to ensure an acceptable riding surface is provided for bicyclists and pedestrians. Empire State Trail signing and new pavement markings will delineate the trail within the project limits.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 03/14/2019

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
04/12/2019 11/29/2019 11/23/2019 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$552,342 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the MOHAWK VALLEY region and includes the following:

Counties
HERKIMER

02 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
22th Congressional District (John Mannion)

State Senatorial District(s)
51th Senatorial District (Peter Oberacker)

State Assembly District(s)
118th Assembly District (Robert Smullen)
119th Assembly District (Marianne Buttenschon)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Heather Tehan
207 Genesee Street
Utica, NY 13501
Phone: 315-793-6307
Email: heather.tehan@dot.ny.gov
Provide feedback on this project