CULVERT REPAIR / REPLACEMENT PROJECT 24
Project ID No. 280657 , Contract Number D265355
Description
This project will rehabilitate three large culverts and replace two large culverts deficient culverts addressing structural and hydraulic deficiency issues in the Towns of Augusta, Vernon, Westernville and in the City of Rome, all within Oneida County.
Project Overview
Project Status
- The project has been Under Construction.
- The Bid Opening was on 11/21/2024
Project Schedule
| Award of Contract | Original Contract Completion Date* | Estimated Substantial Completion Date* | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 12/27/2024 | 11/29/2025 | N/A |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $2,311,775 | $425,585 | $2,737,360 |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the MOHAWK VALLEY region and includes the following:
Counties
FULTON
HAMILTON
HERKIMER
MADISON
MONTGOMERY
ONEIDA
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)
22th Congressional District (John Mannion)
State Senatorial District(s)
46th Senatorial District (Patricia Fahy)
47th Senatorial District (Erik Bottcher)
49th Senatorial District (Mark Walczyk)
51th Senatorial District (Peter Oberacker)
53th Senatorial District (Joseph A. Griffo)
State Assembly District(s)
101th Assembly District (Brian Maher)
111th Assembly District (Angelo Santabarbara)
117th Assembly District (Ken Blankenbush)
118th Assembly District (Robert Smullen)
119th Assembly District (Marianne Buttenschon)
121th Assembly District (Joe Angelino)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
207 Genesee Street
Utica, NY 13501
Phone: 315-793-6307
Email: heather.tehan@dot.ny.gov