This project proposes to provide pavement rehabilitation on State Route 12 between the Route 5A interchange and Putnam Road, in the Towns of Deerfield, Marcy, and Trenton and City of Utica, Oneida County. The total length of the project is approximately 10 miles (44 lane miles). This includes the Ramps at the State Route 12 and Mulaney Road interchange, Ramps at the State Route 12 and State Route 8 interchange, as well as a section of Mulaney Road (between Town Road and Trenton Road) and Route 926A, Horatio Street, northbound and southbound. Roadside elements to be addressed in this contract include: guiderail, drainage, and signs. Bridge rehabilitation work is limited to concrete repairs and guiderail replacement on the approaches. The overhead sign project proposed work involves the repair and replacement of twenty overhead sign structures in the City of Utica and the towns of Paris, Deerfield in Oneida County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 07/25/2019

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
09/05/2019 11/30/2020 06/30/2021 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$7,637,723 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the MOHAWK VALLEY region and includes the following:

Counties
ONEIDA

Cities
UTICA

Towns
DEERFIELD
MARCY
PARIS
TRENTON

02 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
21th Congressional District (Elise Stefanik)
22th Congressional District (John Mannion)

State Senatorial District(s)
53th Senatorial District (Joseph A. Griffo)

State Assembly District(s)
118th Assembly District (Robert Smullen)
119th Assembly District (Marianne Buttenschon)
122th Assembly District (Brian D. Miller)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Heather Tehan
207 Genesee Street
Utica, NY 13501
Phone: 315-793-6307
Email: heather.tehan@dot.ny.gov
Provide feedback on this project