Rte 825 Bridge Rehabilitation Project

Project ID No. 206702 , Contract Number D264607

Description

This project will rehabilitate the bridges carrying NYS Route 825 over NYS Rte 365 on the ramp from NYS Rte 825 to NYS Rte 49 eastbound, and, NYS Rte 825 over NYS 365 on the ramp from NYS Rte 825 to NYS Rte 49 westbound.  The project in located in the City of Rome, Oneida County.

Issue Description:
BIN 1069750 - Rte 825 over Rte 365 to Rte 49 EB scope of work includes deck replacement, bearing replacement, and concrete repairs on the substructure.  Estimated construction cost = $2.0M. BIN 1069760 - Rte 825 over Rte 365 to Rte 49 WB scope of work includes deck replacement and concrete repairs on the substructure.  Estimated construction cost = $0.700M 11/2021 Letting is planned. Funding from Block PM Project 2TM222

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 11/18/2021

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
12/06/2021 10/30/2022 11/28/2022 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$2,575,821 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the MOHAWK VALLEY region and includes the following:

Counties
ONEIDA

Cities
ROME

02 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
22th Congressional District (John Mannion)

State Senatorial District(s)
53th Senatorial District (Joseph A. Griffo)

State Assembly District(s)
119th Assembly District (Marianne Buttenschon)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Heather Tehan
207 Genesee Street
Utica, NY 13501
Phone: 315-793-6307
Email: heather.tehan@dot.ny.gov
Provide feedback on this project