Route 921C (N. Genesee St) Safety Project
Project ID No. 204712 , Contract Number D265179
Description
This project will address safety issues on North Genesee Street in the City of Utica in the vicinity of the intersections with the NYS Thruway Exit 31 and Interstate 790 ramps to North Genesee St. This project will also improve the landscaping on NYS Routes 5S and 921C,and reduce landscape maintenance requirements in the corridors.
Issue Description:
The intersections of N. Genesee St with the Exit 31 Ramps is a PIL. There are pedestrian, sight distance, and weaving issues in area of the ramps.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 01/25/2024
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 03/07/2024 | 12/31/2024 | 05/21/2025 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $2,332,822 | $252,146 | $2,584,968 |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the MOHAWK VALLEY region and includes the following:
Counties
ONEIDA
Cities
UTICA
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
22th Congressional District (John Mannion)
State Senatorial District(s)
53th Senatorial District (Joseph A. Griffo)
State Assembly District(s)
119th Assembly District (Marianne Buttenschon)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
207 Genesee Street
Utica, NY 13501
Phone: 315-793-6307
Email: heather.tehan@dot.ny.gov