CULVERT RESILIENCY - CROSS SFY 27B
Project ID No. 1LC104
Description
A program to replace and rehabilitate large culverts on the state system with a focus on safety, infrastructure and hydraulic resiliency, supporting the state's economy and environmental stewardship.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Summer 2027.
- Construction is expected to begin in Fall 2027.
- Construction is expected to be completed in Winter 2029/2030.
Cost of the Project
The project cost is approximately $12,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
SARATOGA
WARREN
Towns
CORINTH
LAKE GEORGE
SARATOGA
STILLWATER
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)
State Senatorial District(s)
44th Senatorial District (James Tedisco)
45th Senatorial District (Daniel G. Stec)
State Assembly District(s)
113th Assembly District (Carrie Woerner)
114th Assembly District (Matthew Simpson)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: