CULVERT RESILIENCY - CROSS SFY 26B
Project ID No. 1LC101
Description
Replacement of three culverts on Route 9L (Ridge Road) and Route 9N (Lake Shore Drive) in Warren County and two culverts on Route 9N (Hague Road) and Route 9 in Essex County.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2026/2027.
- Construction is expected to begin in Spring 2027.
- Construction is expected to be completed in Winter 2029/2030.
Cost of the Project
The project cost is approximately $9,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
ESSEX
WARREN
Towns
BOLTON
ELIZABETHTOWN
HAGUE
QUEENSBURY
TICONDEROGA
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
21th Congressional District (Elise Stefanik)
State Senatorial District(s)
45th Senatorial District (Daniel G. Stec)
State Assembly District(s)
114th Assembly District (Matthew Simpson)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: