Pavement Resurfacing Setaside SFY 27 2nd Project
Project ID No. 181152
Description
Resurface pavement as needed to improve conditions in various locations throughout Region 1, including Albany, Essex, Greene, Rensselaer, Saratoga, Schenectady, Warren and Washington counties.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2026/2027.
- Construction is expected to begin in Spring 2027.
- Construction is expected to be completed in Winter 2027/2028.
Cost of the Project
The project cost is approximately $14,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
ALBANY
ESSEX
GREENE
RENSSELAER
SARATOGA
SCHENECTADY
WARREN
WASHINGTON
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: