Project Details

Pavement Resurfacing Setaside SFY 26 2nd Project

Project ID No. 181150 , Contract Number D265716

Description

Resurface pavement at the following sites: Route 9N from Route 74 to existing joint north of Brumbaugh Road, Town of Ticonderoga, Essex County; Route 4 from End Route 29 overlap to End Route 4/32 overlap, Towns of Saratoga and Northumberland, Saratoga County; Route 4 from Ten Broeck Street to Route 32, Town of Stillwater, Saratoga County; Route 50 from Interstate 87 ramp to existing joint/north of Perry Road, Town of Wilton and City of Saratoga Springs, Saratoga County; Route 50 from Start Route 50/67 overlap to existing joint at Front Street, Village of Ballston Spa, Saratoga County; Route 8 from Route 8/9 Loon Lake) to Interstate 87 northbound off ramp, Town of Chestertown, Warren County; Route 9 from Route 254 to Route 149, Town of Queensbury, Warren County; Route 9 from Route 149 to Route 9N South, Town of Lake George, Warren County; Route 22 from Archibald Street to East High Street, Town of Salem, Washington County.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 03/12/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
04/17/2026 11/30/2027 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$15,197,810 $0 $15,197,810 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
ESSEX
SARATOGA
WARREN
WASHINGTON

Cities
SARATOGA SPRINGS

Towns
BALLSTON
CHESTER
LAKE GEORGE
MILTON
NORTHUMBERLAND
QUEENSBURY
SALEM
SARATOGA
STILLWATER
TICONDEROGA
WILTON

Villages
SCHUYLERVILLE
STILLWATER
BALLSTON SPA

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)

State Senatorial District(s)
43th Senatorial District (Jacob Ashby)
44th Senatorial District (James Tedisco)
45th Senatorial District (Daniel G. Stec)

State Assembly District(s)
112th Assembly District (Mary Beth Walsh)
113th Assembly District (Carrie Woerner)
114th Assembly District (Matthew Simpson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project