Resurface pavement as needed to improve conditions at the following locations: Route 9N from County Route 2 Creek Road to Route 185 Bridge Road in the Town of Crown Point and Route 9N from McKenzie Brook to Treble Cliff Way in the Hamlet of Port Henry, Essex County; Route 4 from Bridge over Hudson to Town of Waterford Line in the Town of Waterford, Route 9 from Crossing Blvd to Dunning Street in the Towns of Halfmoon and Malta, and Route 32 from Fulton St to Start Route 4/32 Overlap in the Town of Waterford, Saratoga County; Route 9 from Access to Beach Road to Exit 22 Access Ramps in the Town of Lake George and Route 28N from Essex County Line to North Creek in the Hamlet of North Creek, Warren County; Route 4 from southern Village Line to County Route 18 in the Village of Whitehall, Route 22 from Route 4/32 to Bellamy Street in the Village of Whitehall, and Route 254 from Warren St to St Paul's Drive in the Village of Hudson Falls, Washington County.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 03/28/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
04/26/2024 12/31/2025 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$16,852,279 $568,543 $17,420,822 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
ESSEX
SARATOGA
WARREN
WASHINGTON

Towns
CHESTER
CLIFTON PARK
CROWN POINT
HALFMOON
JOHNSBURG
KINGSBURY
LAKE GEORGE
MALTA
MOREAU
MORIAH
WATERFORD
WHITEHALL

Villages
HUDSON FALLS
LAKE GEORGE
ROUND LAKE
SOUTH GLENS FALLS
WATERFORD
WHITEHALL

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)

State Senatorial District(s)
44th Senatorial District (James Tedisco)
45th Senatorial District (Daniel G. Stec)

State Assembly District(s)
108th Assembly District (John T. McDonald III)
112th Assembly District (Mary Beth Walsh)
113th Assembly District (Carrie Woerner)
114th Assembly District (Matthew Simpson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project