Project Details

Pavement Corrective Maintenance SFY 23

Project ID No. 181143 , Contract Number D264969

Description

Resurface pavement on State Route 7 from Interstate 87 to Interstate 787, Town of Colonie, Albany County; State Route 7 from Route 278 to Tomhannock Reservoir, Town of Brunswick, Rensselaer County; State Route 7 from 5 Corners to Altamont, Town of Rotterdam, Schenectady County; State Route 9J from Rensselaer County Line to Village of Castleton Line, Town of Schodack, Rensselaer County; State Route 23 from Schoharie Creek to Route 23A. Towns of Prattsville and Ashland, Greene County; State Route 23 from South Street CR 12 to State Route 296, Town of Windham, Greene County; State Route 23A from Route 23 to Airport Road, Town of Prattsville, Greene County; State Route 32 from CSX RR to Elm Avenue, Town of Bethlehem, Albany County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 03/09/2023

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
03/30/2023 12/20/2024 09/13/2024 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$14,263,114 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
ALBANY
GREENE
RENSSELAER
SCHENECTADY

Towns
BETHLEHEM
BRUNSWICK
COLONIE
PITTSTOWN
PRATTSVILLE
ROTTERDAM

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)

State Senatorial District(s)
41th Senatorial District (Michelle Hinchey)
43th Senatorial District (Jacob Ashby)
46th Senatorial District (Patricia Fahy)

State Assembly District(s)
102th Assembly District (Chris Tague)
107th Assembly District (Scott Bendett)
110th Assembly District (Phil Steck)
111th Assembly District (Angelo Santabarbara)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project