PAVEMENT CORRECTIVE MAINTENANCE SFY20C
Project ID No. 181068 , Contract Number D264208
Description
Pavement maintenance at the following sites: US Route 9 from Lansing Lane to State Route 146 in the Town of Halfmoon and State Route 9N from Myrtle Street to North Greenfield Road/Spier Falls Road in the City of Saratoga Springs and Town of Greenfield; Saratoga County. And US Route 2 from Stewart Road to the Massachusetts State Line in the Town of Petersburgh and State Route 150 from US Routes 9/20 to Best Road in the Towns of Sand Lake and Schodack; Rensselaer County.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 03/19/2020
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 04/22/2020 | 11/15/2021 | 10/19/2021 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $11,445,279 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
RENSSELAER
SARATOGA
Cities
SARATOGA SPRINGS
Towns
GREENFIELD
HALFMOON
PETERSBURGH
SAND LAKE
SCHODACK
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)
State Senatorial District(s)
43th Senatorial District (Jacob Ashby)
44th Senatorial District (James Tedisco)
State Assembly District(s)
107th Assembly District (Scott Bendett)
112th Assembly District (Mary Beth Walsh)
113th Assembly District (Carrie Woerner)
114th Assembly District (Matthew Simpson)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: