Project Details

RUSTIC RAIL REPLACEMENT SFY18

Project ID No. 180974 , Contract Number D263710

Description

Replace rustic guiderail in Region 1 during State Fiscal Year 18/19, which runs from April 1, 2018 to March 31, 2019. Routes 9N, 9, 22, 28, 74, and 185; Essex and Warren Counties. Route 9N; Towns of Jay, Keene, Elizabethtown, and Westport. Route 9; Towns of Schroon, North Hudson, Elizabethtown, Lewis, and Chesterfield. Route 22; Town of Westport. Route 185; Town of Crown Point. Route 74; Town of Ticonderoga, Essex County. Route 28; Town of Johnsburg. Route 9N; Towns of Lake George and Lake Luzerne, Warren County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 05/17/2018

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
06/11/2018 06/30/2019 07/31/2019 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$2,585,596 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
ESSEX
WARREN

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project