PAVEMENT MAINTENANCE SFY18 2ND PROJECT
Project ID No. 180968 , Contract Number D263693
Description
Conduct preventative maintenance and/or repair pavement to improve conditions at the following locations: State Route 20 from the intersection with the Northway to the Town of Guilderland/City of Albany line, Town of Guilderland, Albany County; State Route 32 from the intersection with the on/off ramps for Exit 6 of Interstate 787 to just south of the State Route 378 overpass, Village of Menands, Albany County; Feura Bush Road (State Reference Route 910A) from the intersection with State Route 32 to the intersection with State Route 144, Town of Glenmont, Albany County; Balltown Road (State Reference Route 914T) from the intersection with State Route 5 to the intersection with State Route 7, Town of Niskayuna, Schenectady County; State Route 9N from the bridge over the Hudson River to the intersection with State Route 9, Town of Lake Luzerne, Warren County.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 04/19/2018
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 05/23/2018 | 11/30/2018 | 08/22/2019 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $7,575,858 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: Yes
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
ALBANY
GREENE
SCHENECTADY
WARREN
Cities
ALBANY
SCHENECTADY
Towns
ATHENS
BETHLEHEM
GUILDERLAND
LAKE GEORGE
LAKE LUZERNE
NISKAYUNA
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
19th Congressional District (Josh Riley)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)
State Senatorial District(s)
41th Senatorial District (Michelle Hinchey)
44th Senatorial District (James Tedisco)
45th Senatorial District (Daniel G. Stec)
46th Senatorial District (Patricia Fahy)
State Assembly District(s)
102th Assembly District (Chris Tague)
107th Assembly District (Scott Bendett)
109th Assembly District (Gabriella A. Romero)
110th Assembly District (Phil Steck)
114th Assembly District (Matthew Simpson)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: