Project Details

BRIDGE CORRECTIVE MAINTENANCE SFY16 2ND PROJECT

Project ID No. 180898 , Contract Number D263373

Description

This project will repair various bridges throughout the eight counties in Region 1. These are Albany, Essex, Rensselaer, Warren and Washington.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 01/26/2017

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
03/24/2017 12/01/2018 01/30/2020 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$6,394,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: Yes

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
ALBANY
ESSEX
RENSSELAER
WARREN
WASHINGTON

Cities
ALBANY
TROY

Towns
CHESTERFIELD
COLONIE
EAST GREENBUSH
FORT EDWARD
GREEN ISLAND
HOOSICK
LAKE GEORGE
LEWIS
QUEENSBURY

Villages
FORT EDWARD
GREEN ISLAND
LAKE GEORGE
MENANDS

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
19th Congressional District (Josh Riley)
20th Congressional District (Paul Tonko)
21th Congressional District (Elise Stefanik)

State Senatorial District(s)
43th Senatorial District (Jacob Ashby)
45th Senatorial District (Daniel G. Stec)
46th Senatorial District (Patricia Fahy)

State Assembly District(s)
107th Assembly District (Scott Bendett)
108th Assembly District (John T. McDonald III)
109th Assembly District (Gabriella A. Romero)
110th Assembly District (Phil Steck)
113th Assembly District (Carrie Woerner)
114th Assembly District (Matthew Simpson)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project