Replace the deck and provide other structural repairs to the Interstate 90 bridge over Fuller Road. Bridge deck and structural repairs to the Interstate 90 over Erie Blvd Bridge.  Rehabilitation of these Bridges, originally constructed in the 1960's, will extend the useful life providing continued access between the Thruway and the Capital District. The structure is located in City of Albany, Albany County.

Issue Description:
PIN 1528.84.313 has a PAN PIN Setup to charge directly to PIN 1528.82.313 in order to keep the RR Force account related to I-90 over Erie Blvd.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 06/18/2020

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
07/31/2020 11/30/2021 11/30/2021 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$15,349,153 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
ALBANY

Cities
ALBANY

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
20th Congressional District (Paul Tonko)

State Senatorial District(s)
46th Senatorial District (Patricia Fahy)

State Assembly District(s)
109th Assembly District (Gabriella A. Romero)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project