RT. 9P Complete Streets and Pavement Resurfacing, City of Saratoga Springs, Saratoga County
Project ID No. 124709 , Contract Number D264930
Description
Pavement corrective maintenance on State Route 9P (Union Avenue) from Interstate 87 to East Avenue. Includes shoulder widening and installation of bicycle lane and Pedestrian facilities by widening shoulders and installing sidewalk, as well as reestablishment of the center island curb. Route 9P from Regatta View Drive to I-87 will also be resurfaced. City of Saratoga Springs, Saratoga County.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 12/15/2022
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 01/20/2023 | 06/30/2024 | 11/10/2023 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $5,696,115 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: No
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
SARATOGA
Cities
SARATOGA SPRINGS
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
20th Congressional District (Paul Tonko)
State Senatorial District(s)
44th Senatorial District (James Tedisco)
State Assembly District(s)
113th Assembly District (Carrie Woerner)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: