Project Details

INTERSECTION SAFETY ENHANCEMENTS, RT 29 AT ROWLAND ST, TOWN OF MILTON, SARATOGA COUNTY

Project ID No. 123629 , Contract Number D265261

Description

Intersection Safety Enhancements at State Route 29 and Rowland Street. Town of Milton, Saratoga County.

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 07/11/2024

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
08/02/2024 10/30/2025 N/A Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,377,322 $0 $3,377,322 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the CAPITAL DISTRICT region and includes the following:

Counties
SARATOGA

Towns
MILTON

01 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
20th Congressional District (Paul Tonko)

State Senatorial District(s)
44th Senatorial District (James Tedisco)

State Assembly District(s)
112th Assembly District (Mary Beth Walsh)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

History

The New York State Department of Transportation is designing a roundabout to enhance safety and reduce congestion at the intersection of NY State Route 29 (Washington Street), Rowland Street (Saratoga County Route 47) and Petrified Sea Gardens Road in the Town of Milton, Saratoga County. 

The intersection is just west of the City of Saratoga Springs, and provides important access to and from the Spa City for residents and visitors.

Roundabouts are engineered to maximize safety and minimize congestion. Compared to traditional intersections, traffic flows more freely through roundabouts, cutting congestion and commute times. Crashes at roundabouts tend to be less severe because they typically occur at slower speeds. Roundabouts eliminate the need for electric-powered traffic signals, and contribute to aesthetically pleasing landscapes. 

For tips on how to safely navigate a roundabout, check out this helpful instructional video.

The project is located at the intersection of NY State Route 29 and Rowland Street in the Town of Milton and the City of Saratoga Springs in Saratoga County. Petrified Sea Gardens Road extends to the north.

Aerial view of the intersection of NY Route 29, Rowland Street and Petrified Sea Gardens Road in Saratoga County.

Community Outreach

An in-person open house and public hearing was held Monday, Dec. 18, 2023 at the Town of Milton Community Center, located at 310 Northline Road in Ballston Spa. For those unable to attend in person, a virtual/online public hearing was held on Tuesday, Dec. 19. Department engineers were available at both events to answer questions about the project. 

The project will be funded through the Highway Safety Improvement Program (HSIP)

Project Brochure

Reports/Documents

Additional Info/Links

. 

Schedule

Construction is anticipated to begin in 2024 and be completed in 2025.

Photos/Visualizations

Video animation of proposed single-lane roundabout at the intersection of NY State Route 29 and Rowland Street.

Aerial view of the proposed roundabout at the intersection of NY Route 29 and Rowland Street in Saratoga County.

For tips on how to safely navigate a roundabout, check out this helpful instructional video.

Construction Information

Construction is anticipated to begin in summer of 2024 and be completed by spring/summer of 2025. Construction activities are weather dependent and subject to change based on conditions.

Traffic Control Plan

To minimize construction impacts, one lane of traffic in each direction will be maintained on State Route 29. A long-term closure and detour is anticipated on Petrified Sea Gardens Road. A weekend closure and short-term detour is anticipated on Rowland Street at the intersection.

Businesses near the intersection will remain accessible throughout the duration of construction.

Contact Us:

If you have questions about this project, please contact us:

Scott Cook
50 Wolf Road
Albany, NY 12232
Phone: 518-485-7768
Email: scott.cook@dot.ny.gov
Provide feedback on this project