RT. 9 OVER I-90 (EXIT 11) BRIDGE REPAIR/REPLACE, BIN 1092730
Project ID No. 104357
Description
This project will make repairs to the bridge carrying State Route 9 over Interstate 90 in the vicinity of Exit 11. Town of Schodack, Rensselaer County.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Winter 2027/2028.
- Construction is expected to begin in Spring 2028.
- Construction is expected to be completed in Fall 2028.
Cost of the Project
The project cost is approximately $18,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
RENSSELAER
Towns
SCHODACK
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
21th Congressional District (Elise Stefanik)
State Senatorial District(s)
43th Senatorial District (Jacob Ashby)
State Assembly District(s)
107th Assembly District (Scott Bendett)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: