RT. 5 CENTRAL AVE DRAINAGE REPAIR AND PAVEMENT RESURFACING PART 2
Project ID No. 103426 , Contract Number D265864
Description
Pavement resurfacing and draining repair on State Route 5 (Central Avenue) from State Route 155 to City of Albany Line. Town of Colonie, Albany County.
Project Overview
Project Status
- The current status of the project is In Development.
- The Bid Opening is expected to be in Fall 2026.
- Construction is expected to begin in Winter 2026/2027.
- Construction is expected to be completed in Summer 2027.
Cost of the Project
The project cost is approximately $10,000,000 .
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Location
This project is located in the CAPITAL DISTRICT region and includes the following:
Counties
ALBANY
Towns
COLONIE
Villages
COLONIE
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
20th Congressional District (Paul Tonko)
State Senatorial District(s)
43th Senatorial District (Jacob Ashby)
State Assembly District(s)
110th Assembly District (Phil Steck)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us: