Project Details

Overhead Sign Structure Replacement

Project ID No. 0SSR25 , Contract Number D265804

Description

This project proposes to replace various overhead sign structures to maintain their structural integrity: 1. Southern State Pkwy, Town of Hempstead, Nassau County a. e/b at Exit 15 (Corona Ave/Franklin Ave) c. e/b at Exit 20S (South Grand Ave) d. w/b at Exit 20N (North Baldwin Rd) e. e/b west of Park Ave 2. Meadowbrook State Pkwy, Town of Hempstead, Nassau County a. n/b at Exit M6E (Southern State Pkwy) b. n/b south of NY24 (Hempstead Tpk) c. n/b at Exit M2W (Shopping Mall) 3. Meadowbrook State Pkwy n/b at exits to Northern State Pkwy, Town of North Hempstead, Nassau County 4. Southern State Pkwy e/b west of North Broadway, Town of Oyster Bay, Nassau County 5. Interstate 495 (Long Island Expy), Town of Oyster Bay, Nassau County a. west of South Oyster Bay Rd, b. east of NY135 (Seaford - Oyster Bay Expy), 6. Sunrise Hwy South Service Rd at exit to e/b NY109 (Farmingdale Rd), Town of Babylon, Suffolk County 7. Interstate 495 (Long Island Expy), Town of Huntington, Suffolk County a. e/b west of Exit 50 (Bagatelle Rd) 8. Sunrise Hwy South Service Rd at exits to CR13 (5th Ave) s/b, Town of Islip, Suffolk County 9. Northern State Pkwy e/b east of Harned Rd, Town of Smithtown, Suffolk County 10. CR46 (William Floyd Pkwy) s/b ramp to w/b Interstate 495 (Long Island Expy), Town of Brookhaven, Suffolk County 11. NY25 (Middle Country Rd) w/b east of ramp to n/b CR46 (William Floyd Pkwy), Town of Brookhaven, Suffolk County

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 07/16/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
08/05/2026 02/24/2028 01/25/2028 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$5,756,313 $0 $5,756,313 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the LONG ISLAND region and includes the following:

Counties
NASSAU
SUFFOLK

Towns
BABYLON
BROOKHAVEN
HEMPSTEAD
HUNTINGTON
ISLIP
NORTH HEMPSTEAD
OYSTER BAY
SMITHTOWN

10 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)
3rd Congressional District (Thomas R. Suozzi)
4th Congressional District (Laura Gillen)

State Senatorial District(s)
2nd Senatorial District (Mario R. Mattera)
3rd Senatorial District (Dean Murray)
4th Senatorial District (Monica R. Martinez)
5th Senatorial District (Steven D. Rhoads)
6th Senatorial District (Siela A. Bynoe)
7th Senatorial District (Jack M. Martins)
8th Senatorial District (Alexis Weik)
9th Senatorial District (Patricia Canzoneri-Fitzpatrick)

State Assembly District(s)
002th Assembly District (Jodi Giglio)
003th Assembly District (Joe DeStefano)
007th Assembly District (Jarett Gandolfo)
008th Assembly District (Michael J. Fitzpatrick)
010th Assembly District (Steve Stern)
011th Assembly District (Kwani B. O'Pharrow)
013th Assembly District (Charles D. Lavine)
014th Assembly District (David G. McDonough)
015th Assembly District (Jake Blumencranz)
017th Assembly District (John K. Mikulin)
018th Assembly District (Noah Burroughs)
019th Assembly District (Edward P. Ra)
021th Assembly District (Judy Griffin)
022th Assembly District (Michaelle C. Solages)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 10 Regional Public Involvement Coordinator (RPIC)
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov
Provide feedback on this project