Description

This project proposes installing/upgrading of sidewalk curb ramps and repairing/replacement of sidewalk segments to meet current Americans with Disabilities Act and Department standards on NY25A from Nassau Suffolk Line to Bread & Cheese Hollow Road, NY24 from Meadowbrook State Parkway to NY110, NY 27 from Church Lane to Ocean Road in the Towns of Hempstead, Oyster Bay, Babylon, Huntington and Southampton, Nassau and Suffolk Counties.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 07/25/2019

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
10/22/2019 06/01/2021 05/27/2021 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,326,325 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the LONG ISLAND region and includes the following:

Counties
NASSAU
SUFFOLK

Towns
BABYLON
HEMPSTEAD
HUNTINGTON
OYSTER BAY
SOUTHAMPTON

Villages
FARMINGDALE
NORTHPORT

10 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)
3rd Congressional District (Thomas R. Suozzi)
4th Congressional District (Laura Gillen)

State Senatorial District(s)
1st Senatorial District (Anthony H. Palumbo)
2nd Senatorial District (Mario R. Mattera)
4th Senatorial District (Monica R. Martinez)
5th Senatorial District (Steven D. Rhoads)
6th Senatorial District (Siela A. Bynoe)
7th Senatorial District (Jack M. Martins)
8th Senatorial District (Alexis Weik)

State Assembly District(s)
001th Assembly District (Tommy John Schiavoni)
010th Assembly District (Steve Stern)
011th Assembly District (Kwani B. O'Pharrow)
012th Assembly District (Keith P. Brown)
015th Assembly District (Jake Blumencranz)
017th Assembly District (John K. Mikulin)
018th Assembly District (Noah Burroughs)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 10 Regional Public Involvement Coordinator (RPIC)
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov
Provide feedback on this project