Project Details

Asphalt Pavement Resurfacing

Project ID No. 081082 , Contract Number D265740

Description

This project proposes to restore the pavement riding surface to a smooth and distress free condition by milling and resurfacing the existing pavement. All proposed pavement work is expected to increase safety and provide a smooth riding surface for vehicular travel for the next 10 to 12 years. 1. NY 27(Sunrise Highway) from Nassau/Suffolk County line to North Monroe Avenue in the Town of Babylon, Suffolk County. 2. NY27 (Sunrise Highway) North and South Service Roads from NY109 (Farmingdale Road) to Udall Road in the Towns of Babylon and Islip, Suffolk County

Project Overview

Project Status

  • The project has been Under Construction.
  • The Bid Opening was on 03/26/2026

Project Schedule

Award of Contract Original Contract Completion Date* Estimated Substantial Completion Date* Construction Schedule Variance from Contract Award**
05/05/2026 02/28/2027 01/29/2027 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$16,578,000 $0 $16,578,000 Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the LONG ISLAND region and includes the following:

Counties
SUFFOLK

Towns
BABYLON
ISLIP

Villages
LINDENHURST
AMITYVILLE

10 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
2nd Congressional District (Andrew Garbarino)

State Senatorial District(s)
4th Senatorial District (Monica R. Martinez)
8th Senatorial District (Alexis Weik)

State Assembly District(s)
009th Assembly District (Michael Durso)
011th Assembly District (Kwani B. O'Pharrow)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 10 Regional Public Involvement Coordinator (RPIC)
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov
Provide feedback on this project