Bridge Improvement
Project ID No. 081066 , Contract Number D265428
Description
This project proposes to repair the following bridges to help maintain the reliability and integrity of the bridges and thereby assure the continued safety of the traveling public. 1. NY110 (Broad Hollow Road) northbound over Interstate 495 (Long Island Expressway) in the Town of Huntington, Suffolk County 2. NY110 (Broad Hollow Road) southbound over Interstate 495 (Long Island Expressway) in the Town of Huntington, Suffolk County 3. Long Island Expressway South Service Road over the Sagtikos State Parkway northbound ramp to Interstate 495 (Long Island Expressway) eastbound in the Town of Islip, Suffolk County 4. NY454 (Veterans Memorial Highway) eastbound over Northern State Parkway westbound in the Town of Smithtown, Suffolk County 5. CR19 (Waverly Avenue) over NY27 (Sunrise Highway) in the Town of Brookhaven, Suffolk County
Project Overview
Project Status
- The project has been Under Construction.
- The Bid Opening was on 04/10/2025
Project Schedule
| Award of Contract | Original Contract Completion Date* | Estimated Substantial Completion Date* | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 07/22/2025 | 11/30/2026 | 10/31/2026 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $7,245,000 | $245,530 | $7,490,530 |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the LONG ISLAND region and includes the following:
Counties
SUFFOLK
Towns
BROOKHAVEN
HUNTINGTON
ISLIP
SMITHTOWN
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)
State Senatorial District(s)
2nd Senatorial District (Mario R. Mattera)
3rd Senatorial District (Dean Murray)
4th Senatorial District (Monica R. Martinez)
State Assembly District(s)
005th Assembly District (Doug Smith)
007th Assembly District (Jarett Gandolfo)
008th Assembly District (Michael J. Fitzpatrick)
010th Assembly District (Steve Stern)
012th Assembly District (Keith P. Brown)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov