Crack Sealing Contract
Project ID No. 081054 , Contract Number D264944
Description
This project proposes to apply a preventative maintenance treatment to seal cracks and joint overlays and limited pavement repairs. This work will help to maintain and extend the life of the pavement surface and keeps the highway system in a state of good repair. 1. NY25B (Hillside Ave) from Queens/Nassau line to the East Williston LIRR Station, Town of North Hempstead, Nassau 2. NY25B (Hillside Ave) from Northern State Pkwy to NY25 (Jericho Tpk), Town of North Hempstead, Nassau 3. Wantagh State Pkwy from Ocean Pkwy to Northern State Pkwy, Towns of North Hempstead, Oyster Bay & Hempstead, Nassau. 4. Ocean Pkwy from the Meadowbrook State Pkwy to Jones Beach State Park Field 6, Town of Hempstead, Nassau 5. Ocean Pkwy EB from the Jones Beach State Park Field 6 to the Nassau/Suffolk Co line, Town of Hempstead & Oyster Bay, Nassau 6. NY135 (Seaford Oyster Bay Expy) from Merrick Rd to NY24 (Hempstead Tpk), Towns of Hempstead & Oyster Bay, Nassau 7. NY107 (Hicksville Rd) from Merrick Rd to NY24 (Hempstead Tpk), Town of Oyster Bay, Nassau 8. NY106 from NY106/NY107 split to NY25A (Northern Blvd), Town of Oyster Bay, Nassau 9. Ocean Pkwy EB from Nassau/Suffolk line to the start of concrete, Town of Babylon, Suffolk 10. NY110 (New York Ave) from Depot Rd to Henry St, Town of Huntington, Suffolk 11. NY110 (NY Ave) from Lowndes Ave to High St, Town of Huntington, Suffolk 12. Ocean Pkwy from Robert Moses NB to EB ramp to Captree Toll Plaza, Town of Islip, Suffolk 13. NY27 (Sunrise Highway) South Service Rd from Malts Ave to Manor Ln, Town of Islip, Suffolk 14. NY25 (Middle Country Rd) from Mt. Sinai-Coram Rd to Wading River Manor Rd, Towns of Brookhaven & Riverhead, Suffolk 15. NY25A from Wading River Manor Rd to NY25 (Middle Country Rd), Town of Riverhead, Suffolk 16. NY24 (Flanders Rd) from the traffic circle (CR104/CR63) to east of Bellows Pond Rd, Town of Southampton, Suffolk
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 02/02/2023
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 03/06/2023 | 12/20/2024 | 03/19/2024 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $2,565,970 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the LONG ISLAND region and includes the following:
Counties
NASSAU
SUFFOLK
Towns
BABYLON
BROOKHAVEN
HEMPSTEAD
HUNTINGTON
ISLIP
NORTH HEMPSTEAD
OYSTER BAY
RIVERHEAD
SOUTHAMPTON
Villages
MINEOLA
MUTTONTOWN
OLD WESTBURY
WESTBURY
WILLISTON PARK
BROOKVILLE
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)
3rd Congressional District (Thomas R. Suozzi)
4th Congressional District (Laura Gillen)
State Senatorial District(s)
1st Senatorial District (Anthony H. Palumbo)
2nd Senatorial District (Mario R. Mattera)
3rd Senatorial District (Dean Murray)
4th Senatorial District (Monica R. Martinez)
5th Senatorial District (Steven D. Rhoads)
6th Senatorial District (Siela A. Bynoe)
7th Senatorial District (Jack M. Martins)
8th Senatorial District (Alexis Weik)
State Assembly District(s)
001th Assembly District (Tommy John Schiavoni)
002th Assembly District (Jodi Giglio)
003th Assembly District (Joe DeStefano)
004th Assembly District (Rebecca Kassay)
007th Assembly District (Jarett Gandolfo)
009th Assembly District (Michael Durso)
010th Assembly District (Steve Stern)
013th Assembly District (Charles D. Lavine)
014th Assembly District (David G. McDonough)
015th Assembly District (Jake Blumencranz)
016th Assembly District (Daniel J. Norber)
017th Assembly District (John K. Mikulin)
019th Assembly District (Edward P. Ra)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov