Overhead Sign Structure Replacement
Project ID No. 080947 , Contract Number D263039
Description
This project proposes to replace approximately 20 overhead sign structures on Federal Aid Eligible highways in Nassau and Suffolk Counties to maintain their structural integrity. The locations in Nassau County are as follows: NY25 (Jericho Turnpike) eastbound at Jackson Avenue/South Oyster Bay Road in the Town of Oyster Bay, NY25 (Jericho Turnpike) eastbound and westbound at Commonwealth Boulevard in the Town of Hempstead, NY27 (Sunrise Highway) eastbound at Old Sunrise Highway in the Town of Oyster Bay, Marcus Avenue at the Northern State Parkway eastbound entrance in the Town of North Hempstead. The locations in Suffolk County are as follows: I495 (Long Island Expressway) eastbound at Deer Park Avenue in the Town of Huntington, I495 (Long Island Expressway) westbound at NY111 (Wheeler Road) in the Town of Islip, I495 (Long Island Expressway) westbound at Ronkonkoma Avenue in the Town of Brookhaven, I495 (Long Island Expressway) westboundat CR46 (William Floyd Parkway) in the Town of Brookhaven, I495 (Long Island Expressway) South Service Road eastbound at Wicks Road in the Town of Islip, NY27 (Sunrise Highway) eastbound and westbound at Robert Moses Causeway in the Town of Islip, NY27 (Sunrise Highway) eastbound at Brook Avenue in the Town of Islip, NY27 (Sunrise Highway) eastbound at Old Riverhead Road in the Town of Southampton, NY27 (Sunrise Highway) eastbound at Lewis Road in the Town of Southampton, NY27 (Sunrise Highway) South Service Road eastbound at Manor Lane in the Town of Islip, NY109 (Farmingdale Road) eastbound at NY27(Sunrise Highway) in the Town of Babylon, NY231 (Deer Park Ave) southbound at NY27(Sunrise Highway) in the Town of Babylon.
Project Overview
Project Status
- The project has been Completed Project.
- The Bid Opening was on 12/17/2015
Project Schedule
| Award of Contract | Original Contract Completion Date* | Substantially Completed | Construction Schedule Variance from Contract Award** |
|---|---|---|---|
| 01/26/2016 | 08/08/2017 | 05/15/2018 |
|
**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
| Contract Award Cost | Approved Cost Changes | Current Construction Contract Cost | Cost Variance of Construction Contract** |
|---|---|---|---|
| $3,777,814 | N/A | N/A |
|
**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost
This project receives funding from the following sources:
Federal: Yes
State: Yes
Local: No
*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
Location
This project is located in the LONG ISLAND region and includes the following:
Counties
NASSAU
SUFFOLK
Towns
BABYLON
BROOKHAVEN
HEMPSTEAD
HUNTINGTON
ISLIP
OYSTER BAY
SOUTHAMPTON
Villages
BELLEROSE
Legislative District:
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)
3rd Congressional District (Thomas R. Suozzi)
4th Congressional District (Laura Gillen)
State Senatorial District(s)
1st Senatorial District (Anthony H. Palumbo)
2nd Senatorial District (Mario R. Mattera)
3rd Senatorial District (Dean Murray)
4th Senatorial District (Monica R. Martinez)
7th Senatorial District (Jack M. Martins)
8th Senatorial District (Alexis Weik)
9th Senatorial District (Patricia Canzoneri-Fitzpatrick)
State Assembly District(s)
001th Assembly District (Tommy John Schiavoni)
003th Assembly District (Joe DeStefano)
005th Assembly District (Doug Smith)
006th Assembly District (Phil Ramos)
007th Assembly District (Jarett Gandolfo)
009th Assembly District (Michael Durso)
010th Assembly District (Steve Stern)
011th Assembly District (Kwani B. O'Pharrow)
015th Assembly District (Jake Blumencranz)
022th Assembly District (Michaelle C. Solages)
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.
Contact Us:
If you have questions about this project, please contact us:
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov