Project Details

PM Drainage Clean/Repair/Replace

Project ID No. 080931 , Contract Number D263160

Description

This project proposes to repair and upgrade existing drainage systems at the following locations in Suffolk County to maintain their reliability and integrity and help assure the continued safety of the traveling public: NY114 - beneath the LIRR Bridge e/o Cove Hollow Road, NY114 - Toilsome Lane and Buell Lane, NY27 - around RM 1613, NY25 at Edwards Avenue, NY25 at Tangers Outlets driveway merging with WB NY25, NY27 - Fifth Avenue to Brentwood Road, NY25A - Bread and Cheese Hollow Road to the end at NY25, LIE - Exit 52 to Exit 73.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 04/21/2016

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
05/13/2016 04/30/2018 09/01/2018 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,887,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: No

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the LONG ISLAND region and includes the following:

Counties
SUFFOLK

Towns
BROOKHAVEN
EAST HAMPTON
HUNTINGTON
ISLIP
RIVERHEAD
SMITHTOWN
SOUTHAMPTON

Villages
ISLANDIA

10 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)

State Senatorial District(s)
1st Senatorial District (Anthony H. Palumbo)
2nd Senatorial District (Mario R. Mattera)
3rd Senatorial District (Dean Murray)
4th Senatorial District (Monica R. Martinez)
8th Senatorial District (Alexis Weik)

State Assembly District(s)
001th Assembly District (Tommy John Schiavoni)
002th Assembly District (Jodi Giglio)
003th Assembly District (Joe DeStefano)
005th Assembly District (Doug Smith)
006th Assembly District (Phil Ramos)
007th Assembly District (Jarett Gandolfo)
008th Assembly District (Michael J. Fitzpatrick)
012th Assembly District (Keith P. Brown)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 10 Regional Public Involvement Coordinator (RPIC)
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov
Provide feedback on this project