Project Details

NY110 Pedestrian Safety Improvements

Project ID No. 011260 , Contract Number D263735

Description

This project proposes to provide upgraded pedestrian facilities that focus on pedestrian safety on NY110 between NY27A (Montauk Highway), Town of Babylon and Youngs Hill Road, Town of Huntington including realignment of existing left turn lanes between Detroit Place and Lyons Street to improve sight distance, install new traffic signals and rebuild existing signals, install new crosswalks at existing signalized intersections, reconstruct intersections to provide additional opportunities to cross safely, install pedestrian refuge islands at locations where pedestrians could be stranded in the middle of the road, and install Rectangular Rapid Flash Beacons at crosswalks to enhance safety. The project is located in the Towns of Huntington and Babylon in Suffolk County.

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 06/07/2018

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
07/23/2018 03/04/2020 09/18/2020 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$3,980,020 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the LONG ISLAND region and includes the following:

Counties
SUFFOLK

Towns
BABYLON
HUNTINGTON

Villages
AMITYVILLE

10 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
1st Congressional District (Nick LaLota)
2nd Congressional District (Andrew Garbarino)

State Senatorial District(s)
2nd Senatorial District (Mario R. Mattera)
4th Senatorial District (Monica R. Martinez)
8th Senatorial District (Alexis Weik)

State Assembly District(s)
010th Assembly District (Steve Stern)
011th Assembly District (Kwani B. O'Pharrow)
012th Assembly District (Keith P. Brown)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 10 Regional Public Involvement Coordinator (RPIC)
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov
Provide feedback on this project