NY347 & NY112 Intersection Reconstruction

Project ID No. 005421 , Contract Number D262168

Description

This project is part of the NY Route 347 safety, mobility and environmental improvement project presented at the January 29, 2009 open house. The limits of work on NY Route 347 are from Jayne Boulevard to Davis Avenue, in the town of Brookhaven, Suffolk County. This project proposes to construct a jughandle along Rose Lane / Canal Road / Sylvan Lane in the southeast quadrant of NY Route 347 and NY Route 112 to relieve traffic congestion at these intersections. The proposed improvements along NY Route 347 include three travel lanes in each direction, raised medians, left turn lanes, and continuous sidewalk on the north side and a separate shared-use path for bicycles and pedestrians on the south side. NYSDOT is cooperatively working with the town of Brookhaven in their development of a small park in the southeast quadrant of the NY Route 347 and NY Route 112 intersection. This park would provide a greenway stop to the bicyclists and pedestrians, as well as a recreation area and green gateway to the local community

Project Overview

Project Status

  • The project has been Completed Project.
  • The Bid Opening was on 01/10/2013

Project Schedule

Award of Contract Original Contract Completion Date* Substantially Completed Construction Schedule Variance from Contract Award**
03/26/2013 01/27/2015 07/30/2015 Schedule Variance Indicator

**Schedule Variance Key:
● Red - Current Schedule Variance is > 10% of Original Completion
● Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
● Green - Current Schedule Variance is within 5% of Original Completion

Construction Costs

Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$25,577,000 N/A N/A Cost Variance Indicator

**Cost Variance Key:
● Red - Current Construction Costs are > 10% of Contract Award Cost
● Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
● Green - Current Construction Costs are within 5% of Contract Award Cost

This project receives funding from the following sources:

Federal: Yes

State: Yes

Local: No

*Project Schedule Definitions:
Original Contract Completion Date - This is a contractual date,at the time the Contractor is Awarded the contract, representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.

Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.

Location

This project is located in the LONG ISLAND region and includes the following:

Counties
SUFFOLK

Towns
BROOKHAVEN

10 Region Map

Legislative District:

This project falls within the geographical boundaries of the following legislative districts:

U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten

U.S. Congressional District(s)
1st Congressional District (Nick LaLota)

State Senatorial District(s)
1st Senatorial District (Anthony H. Palumbo)

State Assembly District(s)
004th Assembly District (Rebecca Kassay)

Statewide Transportation Improvement Program (STIP)

The Statewide Transportation Improvement Program (STIP) is a list of every project in New York State for which Federal funding is proposed to be used and that is scheduled to begin during the designated three Federal fiscal year time frame. To review the STIP Project List by Region please see the STIP Project Report.

Contact Us:

If you have questions about this project, please contact us:

Region 10 Regional Public Involvement Coordinator (RPIC)
250 Veterans Memorial Highway
Hauppauge, NY 11788
Phone: 631-952-6929
Email: r10-rpic@dot.ny.gov
Provide feedback on this project